Navigate Permits, Approvals, and Inspections
Call your building department early to confirm submittal requirements, typical review durations, and inspection scheduling backlogs. Factor seasonal spikes and inspector vacation calendars. In one case, simply pulling a separate electrical permit allowed rough-in earlier, saving two weeks. Comment with your city, and we'll gather real wait-time experiences.